Supporting Road User Comfort, JTT Conducts Maintenance on the Palimanan-Kanci Toll Road
16 September 2026

PRESS RELEASE
PT Jasamarga Transjawa Tol
No. 257/2026
Date: September 16, 2026
Supporting Road User Comfort, JTT Conducts Maintenance on the Palimanan-Kanci Toll Road
Cirebon (14/09) – PT Jasamarga Transjawa Tol (JTT) is carrying out Flexible Reconstruction and Type 1 Patching works on the Palimanan-Kanci Toll Road as part of its efforts to maintain Minimum Service Standards (SPM) and improve road user safety and comfort.
The work is being carried out in stages to maintain road quality and driving comfort, with the following schedule:
Flexible Reconstruction
-
KM 195+805 to KM 195+760 towards Jakarta, Lane 1, from Monday, September 14, 2026 at 08:00 WIB to Wednesday, September 16, 2026 at 20:00 WIB
-
KM 188+903 to KM 188+863 towards Jakarta, Lane 1, from Wednesday, September 16, 2026 at 08:00 WIB to Saturday, September 19, 2026 at 16:00 WIB
Type 1 Patching Works
-
KM 189+500 towards Semarang, Lane 2
-
KM 196+900 towards Semarang, Lane 1
-
KM 195+650 towards Jakarta, Lane 2
-
KM 192+700 towards Jakarta, Lane 1
Starting Thursday, September 17, 2026 at 08:00 WIB to 17:00 WIB
“The Flexible Reconstruction and Type 1 Patching works are part of the maintenance program to maintain the quality of toll road infrastructure so that it remains reliable and provides comfort for road users. During the work, the toll road will remain operational with situational traffic management measures around the work locations,” explained Ginanjar.
Acting VP of Corporate Secretary and Legal of JTT, Dary Achmad Budi, also stated that JTT has prepared operational mitigation measures, including the installation of work safety signs in accordance with standards, deployment of personnel in the field, and intensive coordination with the Police to ensure smooth traffic flow during the work.
Dary expressed his apologies for any potential inconvenience that road users may experience during the work.
“We apologize for any potential inconvenience or traffic congestion that may occur during the maintenance work. This work is part of JTT’s commitment to maintaining service quality and the reliability of toll road infrastructure. We appreciate the patience and understanding of road users during the work,” said Dary.
JTT urges road users to anticipate their travel time, ensure that both their vehicles and drivers are in good condition, maintain sufficient electronic toll card balances, and comply with traffic signs and instructions from officers in the field.
The latest traffic information is available through the Travoy application or Jasa Marga Group One Call Center 133.
—————————————————
For further information, please contact:
-
Ginanjar Bekti Rakhmanto
Senior Manager
Representative Office 2 Palikanci
PT Jasamarga Transjawa Tol
Jl. Jenderal Sudirman No. 138
Ciperna-Cirebon 45171 -
Dary Achmad Budi
Acting VP of Corporate Secretary and Legal
PT Jasamarga Transjawa Tol
Jl. Teuku Umar, Sepanjang Jaya, Rawa Lumbu Bekasi - 17114
Email: jasamarga.transjawa@jasamarga.co.id
Instagram: @official.jmtransjawa